Engineering Product Innovation Center Construction Activity for the Period of March 25 – March 29

Anticipated construction activities for the week of March 25 – March 29:

1. Site Work – The existing concrete slab in the 744 Comm Ave garage has been removed and the contractor will be conducting pre-excavation and drilling for the helical pile installation.

2. Abatement – The contractor will begin asbestos abatement on the ceiling on the first floor of 750 Comm Ave. (the old Guitar Center space).

3. Mechanical/Electrical/Plumbing – The contractor will begin preparing the applicable mechanical, electrical, and plumbing systems in for subsequent demolition and/or construction. There will be no impact to the classrooms or other areas of the building during this work.