Anticipated construction activities for the week of April 1 – April 5:
1. Site Work – The contractor will be installing the foundations for the new concrete slab.
2. Abatement – The contractor will continue asbestos abatement on the ceiling on the first floor of 750 Comm Ave. (the old Guitar Center space).
3. Demolition – The contractor will begin demolition on the interior walls of 750 Comm Ave.
4. Mechanical/Electrical/Plumbing – The contractor will continue to prepare any project-related mechanical, electrical, and plumbing systems for subsequent demolition and/or construction. Building occupants will experience no effects from this work.