Myles Standish Hall – Construction Activity – 9/23/17 to 9/29/17
For 9/23/17 to 9/29/17:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday Work – 9/23/17
- Coring – Floors 2-9
- Clean up and loadout – Bay State Road
- Rigging rooftop equipment to roof – Crane set up on Beacon Street (One lane of traffic will be closed on Beacon Street during this activity.)
Demolition/Loadout
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
- Exterior façade demolition – Beacon Street
Masonry Restoration (Exterior – Bay State Road & Beacon Street)
- Continue with masonry restoration and demolition – Bay State Road & Beacon Street
Roof Myles (Exterior)
- Install parapet blocking
- Install rooftop steel
- Penthouse construction
For questions, please contact Brian Kelley or visit our website for more information.