Myles Standish Hall – Construction Activity – For 2/24/18 to 3/2/18

Myles Standish Hall - Construction Activity - For 2/24/18 to 3/2/18 Myles Standish Hall - Construction Activity - For 2/24/18 to 3/2/18

For 2/24/18 to 3/2/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 2/24/18

  • Interior work
  • Exterior caulking
  • Hoist removal
  • Clean up and loadout

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Install Fraco at lift 26 and start restoration work where man and material hoist was located

Man and Material Hoist

  • Crane will be onsite to remove the man and material hoist

 Roof Myles (Exterior)

  • MEP insulation

View all posts