Myles Standish Hall – Construction Activity – 10/7/17 to 10/13/17

Myles Standish Hall - Construction Activity - 10/7/17 to 10/13/17

For 10/7/17 to 10/13/17:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

 Saturday Work – 10/7/17

  • Coring – Floors 2-9
  • Clean up and stocking exterior staging
  • Clean up and loadout – Bay State Road

 Monday 10/9/17 – No work– Columbus Day

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps
  • Exterior façade demolition – Beacon Street

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street

Roof Myles (Exterior)

  • Install parapet blocking
  • Install rooftop steel
  • Penthouse construction

For questions, please contact Brian Kelley or visit our website for more information.