Myles Standish Hall – Construction Update – 5/17/18

 Myles Standish Hall - Construction Update - 5/17/18  Myles Standish Hall - Construction Update - 5/17/18

For 5/19/18 to 5/25/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

Saturday Work – 5/19/18 – 7 am to 5 pm

  • Clean up and loadout
  • Interior work
  • Exterior site work

Myles – 7 am to 6 pm

Demolition / Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps.

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demo at Beacon and Bay State Road
  • Restoration of façade at hoist location

Roof (Exterior)

  •  MEP insulation

Site

  • Myles
    • Demo sidewalks and start underground
  •  Point Park
    • Continue with excavation and underground
    • Pour concrete at sidewalks
    • Start installation of pavers
  • Charlesgate
    • Continue with Charlesgate bump out construction

Annex – 7 am to 6 pm

Demolition / Loadout

  • Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps.

Site

  • Set up site fencing at Raleigh Street
  • Demo sidewalks / vault

Roof

  • Masonry restoration
  • Roof removal and re-installation

Masonry Restoration

  • Beacon Street & Raleigh Street – Start façade restoration

View all posts